BMS HEAD END
Checked BMS PC hard drive performance and found satisfactory.
Checked BMS PC hardware and found all operating as required.
Carried out Optergy Database and Job backup and stored securely.
Carried out full system backup of Envision and stored securely.
FAN COIL
UNITS
Checked performance of control loop against setpoints and found to be operating as designed.
Verified operational status of all units
Tested actuator and/or duct heater operation
Checked validity of occupied/unoccupied schedules.
Checked trendlogs
VAV's
Checked performance of control loop against setpoints and found to be operating as designed.
Verified operational status of all units
Tested actuator and/or duct heater operation
Checked validity of occupied/unoccupied schedules.
Checked trendlogs
PACKAGED AIR-CONDITIONING UNITS
Checked performance of control loop against setpoints and found to be operating as designed.
Verified operational status of all units
Tested control interface and found to be operating satisfactorily.
Checked validity of occupied/unoccupied schedules.
Checked trendlogs
CO/CO2 CALIBRATION
Verified CO/CO2 sensors readings
LOCAL ZONE TEMPERATURE VERIFICATION
Verified zone temperature sensors readings